1. General
Welcome
to the Santa Lucia Apartments! Accompanied by grace and help
from lots of different people, Ken and Melissa Moholt-Siebert are able
to present
you a tour of this transformed apartment building as it neared
completion.
In brief,
the building was substantially gutted and re-built, with all new electrical,
telecommunications, plumbing and heating systems installed. The
basement was converted to living space. The number of units remained
eight, but as the total floor area was increased from approximately 6000 sf
to 9000, the size of the units increased. Formerly, there were two studios and six 1-bedroom
units. The studio units disappeared. We now have four
1-bedroom units, three large 2-bedrooms units and one 3-bedroom
unit. Of course, the condition of the units has been greatly
improved.
We pursued
a fast-track process after purchasing the building: We began some
work (the back stairs, for example) first, while the building was
still occupied. then, when access to all the units was available
we began work that could be permitted with a permit that
could be obtained over-the-counter. (For example, asbestos
abatement, select demolition, new window and door opeings). We
had to wait then for the permit that allowed the actual reconfiguration
of the unit layout, as the review for that work is much more
complicated. You
are seeing the building a little over 100 days after the full
permit.
Exterior
paint and landscaping continued for another
month after most of these photos were taken.
2.
Exterior Front (and sides).
The building already
had a stucco
facade when purchased. However, it was a bit plain. A few
eave
brackets,
some window boxes and little trellis over the entry, plus some paint, give the
building a whole new
aspect. An entry court with masonry walls replaces the lawn. The
walls add a sense of security in addition
to hiding the garbage (which was an eysore
before). Plantings are selected for a sub-tropical theme. A
gurgling pool is being prepared on the east side. Custom lamp
standards are planned for the front gate way.
Electrical
service, formerly overhead (and woefully
inadequate), is now underground from the pole to the service equipment on
the west side of
the building. The gas meters are located adjacent to the
electrical service, having been removed from inside the building.
A 1700 gallon oil tank
was removed. It had been located about 12 feet down, between the curb
and the sidewalk on the east side.
The retaining walls on the sides,
the sidewalk and the all the paving on the site is all new.
The
old asbestos shingles have been removed from the building sides and back and
have been replaced
with horizontal lap siding. The window trim has been
restored. (It had been cut down to narrow trim for the asbestos
siding).
3.
Entry, Foyer, Stairs
The entry door has been
refinished. Intercom and keypad entry are new. The whole building is provided with zoned alarm
wiring. The old mailboxes are planned to be replaced by new ones.
When purchased,
two symmetrical stairs led up to the upper
floor units, one to the
units on that side, the other for the other side.
The openings at the far ends led to open common hallways. Now one stair
has been redirected down to serve the
basement units; and, the openings at each end have the entry doors to
the first floor units.
Please proceed
up the stairs.

5.
Upstairs Hall
This upstairs hall has
been made
by combining what was formerly two symmetrical, dingy, dark halls, which were
littered with dust and abandoned steam radiators.
6. Unit 5
All the units upstairs
preserve
their original interior layout. The front units, (5 & 7) have
been changed least. So you are looking now at unit most like all
the units were before, but nonetheless substantially upgraded.
Skylights are new. Wood floors have been (or will be)
refinished. Tile and marmoleum is new. As noted before, all
the plumbing and electrical wiring in this unit and throughout the
building is new. All the gas lines have been replaced.
We did however, retain
the
existing 80% efficient gas furnaces on for these upstairs units, as
they still have a useful life. We anticipate upgrading these
furnaces individually when they need to be replaced.
Note that phone, cable and data
outlets are available in every room.
7.
The Key Lime Bedroom (5)

When purchased, this
bedroom was a
key lime color. Some were sorry to see the color go. Most
were not.


8.
Front Studio/Liv. Room (5)
We brought a gas line
to the middle of the west wall, in case we wish to add a gas fireplace in
the
future. The closet in this room originally housed a murphy bed,
but it was long gone when we purchased the building.


9. Kitchen (5)
We kept the old upper
cabinets. The lower maple cabinets, granite countertops,
marmoleum floor is new.
We have made several
improvements
to this bath to make it feel a bit bigger. The sink was larger
before, and overly constricted the passage. The plumbing chase in the wall
has been shrunk down by 2 to 3
inches on all three sides. The wall at the plumbing side of the
bath/shower used to angle over and restrict the space.
This was because
there is a dining room hutch on the other
side in the other unit. We cut down the hutch to square off the
wall. White tile replaces a formerly dark red floor. the skylight
lightens up the room.
11. Unit 6
The back units upstairs
have been
changed a bit more than the front units. They also have a
different feel than the front units, a difference that existed before
our remodel.

12.
Bath (6)
When we purchased the
building, a
cheap plastic shower was here. We determined that a clawfoot had
originally been located here and we restored that feature. But as
you see, we skipped the feet and boxed the tub in with tile instead
.
The window opens to
a lightwell. Cleaning and painting the lightwell was a huge
job. Our employee, Larry, built platforms and worked in stages
down. Incidentally, notice that both sash work. The
carpenters took apart every old window in the building, re-roped the
weights and reinstalled them.

13.
Liv/Dining with built-in Hutch (6)
The old hutch was cut
down about 2
inches on the left side to accomodate the bathtub on the other
side. The oak floor was here--we had it refinished.

14.
Bedroom (6)
This bedroom is not particularly
sunny, but it was downright dark before. A skylight outside
above the porch admits light to the porch, and the white tile floor
there reflects light into the room. The oak floor is new in this
room. It helps make the room brighter as well.

15.
Kitchen (6)
Before, there were two
back doors to this unit, the door that remains plus another door in the back
wall
on the far right. We added the big window and deleted the extra
door. We also installed the skylight. The room is much
brighter.
The maple cabinets, granite
countertops, and marmoleum floor are new.



16. Back Porch and Stair
(6)
If you look across the
way from the apartment building you
canl see a back stair on the building behind very similar to what
existed on this building before, except that ours, facing south, was
much more rotten. The new porch is much
better. The tile wards against rot and also reflects light into
the rooms. The carpenters, Bill and Don, put quite a few
hours into this stair, especially the curved landing and rail.
We now proceed at
the 2nd floor level (but stay upstairs) across the back balcony to the
unit on the
other side.
17.
Unit 8
Unit
eight is
nearly symmetrical to unit six.
18. Unit 8
Bath
The bathroom is a closer
restoration to the original condition than you've seen so far.
However, as it was originally built in 1908, the floor was fir and the
sink was a corner sink. Also, we changed the sink. We
considered keeping the sink, but it would have cost a lot to refinish
and it wasn't really that great a sink to use.
Unit seven is now the
smallest
unit. The gas line sticking out of the wall in the Living Room is
for a future corner fireplace. The line will be tucked into the
wall until such time as a fireplace is installed.
We proceed back down
the
stairs. At the bottom, we turn left to unit three.
20. Unit 3
At this
point, we need to make a brief historical aside. This building was built in 1908. It
was then a four-plex. There were two units on each of two
floors. The units stretched all the way from the front to the
back of the building. The lighting then was all gas. The
"intercom" was accomplished by speaking tubes. The building had
steam heat from a central boiler in the basement. A two-story
porch stretched across the front of the building.
In 1927,
the then-owner of the building closed in the porch to add floor area, then
split each unit
into two so that he made a total of eight units. While he was at
it, he upgraded to electric lights and installed a telephone-type
intercom.Then he covered the facade with "mexican" stucco, built the
concrete front steps with iron rails and re-christened the building:
"The Amarillo Apartments".
On this
first floor we have re-combined two units on each side to restore the apartment
to
something like its original layout.
The entry hall of this unit was,
when we purchased the building, a common hallway.
21.
Vestibule (former
entry) (3)
This vestibule was formerly the
entry of the front unit.
22.
Bedroom/Studio (3)
This was formerly the
main room of
the front, studio apartment. When we demo'd the plaster in this
room (and the symmetrical room in unit 4) we discovered no fewer than
three ceilings!
23. Bedroom
(former
kitchen) (3)
When we purchased
the building, this was the kitchen for the front unit. We
added the closet.
24. Bath (3)
You will recall the small
bath
upstairs now. This is much the same, though without the skylight.
25. Closet (former common
hallway) (3)
This closet used to be
part of the
common hallway. It wrapped behind the stairs going up. The
floor is raised now to allow headroom for the stair leading to the
basement.
26. New 92% Furnace with
A/C
These units have new
high-efficiency furnaces with air-conditioning.
27. Bath (3)
This bath is very like the one
immediately above in unit seven.
28.
Dining Room with new Arch (3)
Formerly, the hallway
reached a stop before the back room and you had to take a small door into
the
dining room. We have opened the hall to the room beyond, and
added the arch. It opens the room up quite a bit. We will
re-finish the fir floor. The hallway will be carpeted.
29. Living Room (3)
This room used to be
much
smaller. We enclosed a small, rather useless back porch to make
the room larger. The windows simply moved from the old location
to the new. There is a gas line for a future gas fireplace behind
the wall between the lights. This room will be carpeted.

30.
Kitchen (3)
We added the french doors. The
maple cabinets, granite countertops, marmoleum floor are new.



31. Terrace
(3)
The new south-facing
terrace is a
wecome addition. The floor is colored concrete. The walls
are split-face concrete block with colored grout, and a brick cap.
32. Back Patio
The back patio is in progress.
We proceed to unit four on
the opposite side.
33.
Unit 4
This unit is like unit three.
34. Bath (4)
Like the bath above in
unit eight,
this bath retains the "original" form, except that we have replaced the
floor with tile and changed the lavatory.
Now we return to
the front foyer.
35.
New Stairs to Basement
These are the new stairs
added to
the basement. Formerly, a stair went up to the second
floor right-hand apartments. The stairs will be carpeted.

36.
Basement Units-General
In order to build these units,
we had to clear out the basement of an enormous quantity of junk and storage
areas. We had to remove
about 300 feet of
4" schedule 40 steam pipe (all wrapped with asbestos). We had to
get rid of the old boiler. Yuri's crew broke up the old slab and
removed about 18 inches of dirt. Then we cut new window openings
all around, broke up that concrete and hauled it out. There's a good
picture of our little Subaru
hanging through one of the
window openings. Ken had just used the car as a bulldozer to knock
the concrete in--but went too far! The new plumbing was laid in the
ground. Then Yuri's crew moved in about 30 yards of gravel. On
top
of that Phil's crew
placed 6 inches of insulation and a new concrete slab with a special colorant/hardener
on the surface..
The plumbers installed pipes
in the slab for radiant floor heat. Ken used an acid stain over
the concrete and then sealed it.